Quick start:
30 m² rear kitchen extension
2-storey side extension
150 m² detached new house
What are you building?
Extension
Whole new house
Internal floor area: 30 m² (323 sq ft)
Storeys
1
2
3
Finish level
Developer standard
Modern premium
Bespoke luxury
Where in the UK?
London
South East
Midlands / SW
North
Scotland / Wales
Ground type
Normal soil
Clay
Sand
Rock
Site access for diggers & deliveries
Easy
Tight
Through the house / none
Kitchen & bathrooms
New kitchen
Bathrooms
0
1
2
3
Site checks
Trees within ~10 m of the build
Old fuse box / no spare capacity
Contingency: 10%
Optimistic
£78,948
Everything goes right, no surprises
Realistic
£91,590
Includes 10% contingency
Worst case
£101,265
+15% for hidden problems & delays
Per m² (realistic)
£3,053
Materials
£28,650
Labour
£35,850
Start to keys
26 wks (~6.0 mo)
What's in the price
Build shell & structure
£55,500
Kitchen (standard)
£9,000
Professional fees (architect, engineer, Building Control, Party Wall)
£7,740
VAT at 20%
£12,900
Build order & timeline
1. Design & approvals
14w
2. Site prep & groundworks
2w
3. Superstructure & shell
4w
4. First fix
2w
5. Plaster & second fix
2w
6. Fit-out, finishes & handover
3w
Week 0
Week 26
Stage 1: Design & approvals
wk 0–14 · £7,740
Measured survey & architect drawings
Planning permission or permitted-development check (8 wks)
Party Wall notices if near a boundary
Structural engineer calcs
Building Control application
Tender to 3+ builders
Before moving on: Planning decision + Building Regs plans approved
Stage 2: Site prep & groundworks
wk 14–16 · £9,675
Site set-up, welfare, skips
Strip & excavate foundations
Drainage diversion / new runs
Pour foundations
Blockwork to DPC, oversite slab
Before moving on: Building Control: foundation & drainage inspection
Stage 3: Superstructure & shell
wk 16–20 · £22,575
Walls & cavity insulation
Steels / lintels
Floor joists (multi-storey)
Roof structure & covering
Windows & external doors — watertight
Before moving on: Watertight + Building Control structural check
Stage 4: First fix
wk 20–22 · £9,675
Electrics first fix (cables, back boxes)
Plumbing & heating pipework
Ventilation ducting
Stud walls & insulation
Before moving on: Pre-plaster inspection — photograph everything
Stage 5: Plaster & second fix
wk 21–23 · £9,675
Plasterboard & skim (dry 1–2 wks)
Screed floors
Sockets, switches, lights
Radiators / UFH manifold
Doors, skirting, architrave
Before moving on: Electrical cert (Part P) + gas safe cert
Stage 6: Fit-out, finishes & handover
wk 23–26 · £12,900
Kitchen & bathrooms
Flooring & tiling
Decoration
External works & landscaping
Snagging walk-round
Before moving on: Building Control completion certificate
Don't get caught out
Never pay more than 10–15% up front. Pay in stages, only after each checkpoint above is signed off.
Get 3 like-for-like quotes from the same drawings — a quote far below this range usually means "provisional sums" that grow later.
Retain 2.5–5% for 6 months after completion to cover snagging.
Ask for public liability insurance, a written contract (e.g. JCT Homeowner) and a schedule of works.
Print / save tender sheet for builders
Indicative 2026 UK figures — always get written quotes.