What are you building?
Internal floor area: 30 m² (323 sq ft)
Storeys
Finish level
Where in the UK?
Ground type
Site access for diggers & deliveries
Kitchen & bathrooms
Bathrooms
Site checks
Contingency: 10%
Optimistic
£78,948
Everything goes right, no surprises
Realistic
£91,590
Includes 10% contingency
Worst case
£101,265
+15% for hidden problems & delays
Per m² (realistic)
£3,053
Materials
£28,650
Labour
£35,850
Start to keys
26 wks (~6.0 mo)
What's in the price
  • Build shell & structure£55,500
  • Kitchen (standard)£9,000
  • Professional fees (architect, engineer, Building Control, Party Wall)£7,740
  • VAT at 20%£12,900
Build order & timeline
1. Design & approvals
14w
2. Site prep & groundworks
2w
3. Superstructure & shell
4w
4. First fix
2w
5. Plaster & second fix
2w
6. Fit-out, finishes & handover
3w
Week 0Week 26
Stage 1: Design & approvals
wk 0–14 · £7,740
  • Measured survey & architect drawings
  • Planning permission or permitted-development check (8 wks)
  • Party Wall notices if near a boundary
  • Structural engineer calcs
  • Building Control application
  • Tender to 3+ builders
Before moving on: Planning decision + Building Regs plans approved
Stage 2: Site prep & groundworks
wk 14–16 · £9,675
  • Site set-up, welfare, skips
  • Strip & excavate foundations
  • Drainage diversion / new runs
  • Pour foundations
  • Blockwork to DPC, oversite slab
Before moving on: Building Control: foundation & drainage inspection
Stage 3: Superstructure & shell
wk 16–20 · £22,575
  • Walls & cavity insulation
  • Steels / lintels
  • Floor joists (multi-storey)
  • Roof structure & covering
  • Windows & external doors — watertight
Before moving on: Watertight + Building Control structural check
Stage 4: First fix
wk 20–22 · £9,675
  • Electrics first fix (cables, back boxes)
  • Plumbing & heating pipework
  • Ventilation ducting
  • Stud walls & insulation
Before moving on: Pre-plaster inspection — photograph everything
Stage 5: Plaster & second fix
wk 21–23 · £9,675
  • Plasterboard & skim (dry 1–2 wks)
  • Screed floors
  • Sockets, switches, lights
  • Radiators / UFH manifold
  • Doors, skirting, architrave
Before moving on: Electrical cert (Part P) + gas safe cert
Stage 6: Fit-out, finishes & handover
wk 23–26 · £12,900
  • Kitchen & bathrooms
  • Flooring & tiling
  • Decoration
  • External works & landscaping
  • Snagging walk-round
Before moving on: Building Control completion certificate
Don't get caught out
  • Never pay more than 10–15% up front. Pay in stages, only after each checkpoint above is signed off.
  • Get 3 like-for-like quotes from the same drawings — a quote far below this range usually means "provisional sums" that grow later.
  • Retain 2.5–5% for 6 months after completion to cover snagging.
  • Ask for public liability insurance, a written contract (e.g. JCT Homeowner) and a schedule of works.
Indicative 2026 UK figures — always get written quotes.